PROCEDURE TO PROCESS AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021
|
PROCEDURE TO PROCESS AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021 |
|||
|
S. No |
Task |
Responsibility |
Timeline |
|
1 |
USP received in Pakistan Railways Headquarters/Ministry of Railways |
- |
Zero day |
|
2 |
Appraisal by Pakistan Railways |
Relevant officers from MoR and PR |
10 days |
|
3 |
Comments/observations conveyed to unsolicited proponent for revision |
DD/PPP |
2 days |
|
4 |
Revision by unsolicited proponent |
Unsolicited proponent |
7 days |
|
5 |
Project proposal presented to Executive Committee (EC) for assessment of viability |
Executive Committee |
2 days |
|
6 (a) |
If project declared viable by EC, forwarded to P3A for appraisal |
P3A |
10 days |
|
6 (b) |
If declared unviable, same will be communicated to unsolicited proponent |
DD/PPP |
2 days |
|
7 (a) |
In case of qualified project: USP approved for open competitive bidding |
P3A Board |
7 days
|
|
7 (b) |
In case of non-qualified project: USP approved for open competitive bidding |
SRCM |
|
|
8 |
Project advertised for open competitive bidding under PPRA Rule 37(A) |
PR HQs |
|