PROCEDURE TO PROCESS AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021
PROCEDURE TO PROCESS AN UNSOLICITED PROJECT PROPOSAL RECEIVED UNDER PUBLIC PRIVATE PARTNERSHIP AUTHORITY (AMENDMENT) ACT 2021 |
|||
S. No |
Task |
Responsibility |
Timeline |
1 |
USP received in Pakistan Railways Headquarters/Ministry of Railways |
- |
Zero day |
2 |
Appraisal by Pakistan Railways |
Relevant officers from MoR and PR |
10 days |
3 |
Comments/observations conveyed to unsolicited proponent for revision |
DD/PPP |
2 days |
4 |
Revision by unsolicited proponent |
Unsolicited proponent |
7 days |
5 |
Project proposal presented to Executive Committee (EC) for assessment of viability |
Executive Committee |
2 days |
6 (a) |
If project declared viable by EC, forwarded to P3A for appraisal |
P3A |
10 days |
6 (b) |
If declared unviable, same will be communicated to unsolicited proponent |
DD/PPP |
2 days |
7 (a) |
In case of qualified project: USP approved for open competitive bidding |
P3A Board |
7 days
|
7 (b) |
In case of non-qualified project: USP approved for open competitive bidding |
SRCM |
|
8 |
Project advertised for open competitive bidding under PPRA Rule 37(A) |
PR HQs |
|